Page 15 - POPS - Action Plan
P. 15

ACTiON PLAN / 271




        Strategic direction 3. Protect, restore, enhance, and expand natural and historic resources, and
        increase resource-based activities.
        Action 3.1. Update the Urban Forest Master Plan and the Natural Resources Management Plan through a combined
        process.
               Responsible Parties  Potential Partners  Potential funding Sources  Time frame    Cost Range Est.
               DPR               UFC, PRC               Capital budget            short term     $$$
                                                                                  (0–5 years)

        Action 3.2. Protect, restore, and expand natural resources and trees.

               Responsible Parties  Potential Partners  Potential funding Sources  Time frame    Cost Range Est.
        3.2.1.   Address the protection, restoration, and expansion of natural resources in the Four Mile Run planning corridor and master plans for
               parks along Four Mile Run, as well as others leading to riparian areas.
               DPR, DES, CPHD    PRC, UFC, E2C2, NVCT, not-  Capital budget, operating budget  continuous  $$
                                 for-profits, NOVA Parks, City
                                 of Alexandria, community
                                 organizations

        3.2.2.   Pursue easements to protect natural areas, mature tree canopy and heritage resources.
               DPR, DES, CPHD    NVCT, HALRB, property   Capital budget           continuous     $
                                 owners

        3.2.3.   Explore collaboration with the National Park Service to develop master plans for Roaches Run, Gravelly Point, George Washington
               Memorial Parkway, and other NPS areas.
               DPR               NPS                    Capital budget, operating budget,   continuous  $$
                                                        federal funding

        3.2.4.   Collaborate with Arlington Public Schools to identify, preserve, enhance and maintain natural and historic resources on school
               properties
               CPHD, APS, DPR, DES  PTAs, HALRB         Operating budget          continuous     $$

        3.2.5.   Identify opportunities for daylighting streams in public spaces that are currently part of the underground stormwater system.
               DES, DPR, APS     Adjacent property owners  Capital budget         long term      $$$
                                                                                  (10–20 years)

        3.2.6.   Identify opportunities to work with neighboring jurisdictions and state and federal agencies outside of the County.
               DPR               NPS, NOVA Parks, VDOT,   Operating budget        continuous     $
                                 Department of Defense

        3.2.7.   Improve processes for earlier review of public projects, to minimize impact on tree canopy and natural resources.
               DPR, DES, CPHD    PRC, UFC, E2C2         Operating budget          continuous     $


        3.2.8.   Use objective criteria to evaluate whether potential natural resources will be added to the public space system. (See Appendix II for
               land acquisition criteria.)
               DPR, DES          PRC                    Operating budget          continuous     $

        3.2.9.   Identify areas that generate the most heat, also known as urban heat islands, and develop a plan to increase vegetation and tree
               canopy in these areas.
               DPR, DES          UFC                    Operating budget          short term     $$
                                                                                  (0-5 years)









                                                                                                   FINAL DRAFT
   10   11   12   13   14   15   16   17   18   19   20